Since 2005, Pacific Process has been constructing food, beverage, and brewery process plants across New Zealand, Australia, the USA, and Canada, with other regions supported from these locations. Project values range from $1 million to $150 million, and the following represent a cross-section of Pacific Process’s more significant projects.

Dairy

Spray Drying Facility

This plant allowed the client to exploit the growing milk volume in the Reno / Fallon NV area and California. Having the milk standardization capability would also allow the client to export WMP & SMP powders internationally and remain competitive (local USA powder cannot be standardized, and as such would not be competitive in the international powder market). Plant ‘state of the art’ and is considered by the client to be their highest quality facility.

Year: 2012 – 2014

Task: Design and supply of Project Management and Engineering for a 6MT/hr WMP Spray Drying Plant.

Where: Fallon, NV. USA.

Value: US$103M

Features: Project included all disciplines required, including:

  • Civil and building works
  • Milk Treatment & Separation
  • Evaporator and Dryer
  • Cream Pasteurization, handling and load out
  • Powder blending and standardization
  • Services (steam boilers, refrigeration, comp’ air, CIP)
Project 1
Project 2

Dairy Facility

The facility is designed to reduce the number of trucks for transporting Milk out of Province. All water generated from concentration of dairy product re-used in the facility for cleaning of equipment.

Year: 2023 (ongoing)

Task: Design and supply of Project Management and Engineering for a Manufacturing outlet to supply 300M L/year milk concentrate

Where: Blackfalds, Alberta, Canada

Value: CAD$70M

Features: Project included all disciplines required, including:

  • Civil and building works
  • Cold processing facility
  • Bacterial removal system
  • Membrane technology
  • Services
Project 3
Project 4

Secondary Cheese Processing Plant

This new facility allowed the client to close two other processing facilities (natural cheese cutting plant, and their frozen & natural shredded cheese lines), allowing all of their secondary cheese processing to be completed on one processing site.

Year: 2007

Task: Project management and engineering package to supervise and engineer the new plant.

Where: Eltham, NZ.

Value: NZ$60M

Features: Project included all disciplines required, including:

  • Project management and engineering.
  • Civil and building works.
  • Process design and installation.
  • Process line design for processed cheese (IWS & SOS), shred cheese (IQF & Natural) and natural cut
Project 7
Project 8
Project 9

MPC Milk Processing Facility

Plant allows Manitoba dairy farmers the ability to supply all of their milk to the plant. It will produce cream for the Manitoba market, butter for the Canadian market and dry dairy ingredients (milk protein concentrate etc.) for the domestic and international markets

Year: 2017 / 2018

Task: Conversion of an Egg Protein plant to manufacture 150m3/yr MPC

Where: Winnipeg, MB. Canada.

Value: CAD$55M

Features: Project included all disciplines required, including:

  • Civil and building works
  • Milk Treatment & Separation
  • Membranes Systems
  • Cream Handling and Butter Plant
  • Dryer Upgrade
  • Services (steam boilers, refrigeration, comp’ air)
  • WWTP upgrade
Project 10
Project 11

Butter Processing and Packaging

This facility will produce up to 6 MT of Commodity butter products. On either of two production lines fed from a Single butter churn, using SPX Flex line technology.

Year: Current

Task: Design and Build of a turnkey butter plant

Where: Waharoa, NZ

Value: NZ$30M

Features: Project included all disciplines required, including:

  • Civil and building works
  • Cream / buttermilk load out
  • Cream crystallising silos
  • 6 MT/hour Fritz butter plant
  • Palletising
Project 12

IF Plant Management & Engineering

This facility allowed Westland to take the clients DIRA milk, concentrate it and send it to their Hokitika processing plant on the west coast of NZ South Is.

Year: 2012

Task: Project Management & engineering package for WMP Infant Formula plant.

Where: Hokitika, NZ

Value: NZ$25M

Features: Project included all disciplines required, including:

  • Civil and building works
  • Milk delivery to the IF plant
  • Milk storage and handling systems
  • Powder handling & dry blending
Projects Ppl 30
Projects Ppl 29

RO Milk Transfer Station

This facility allowed the client to take DIRA milk, concentrate it and send it to their Hokitika processing plant on the west coast of NZ South Is.

Year: 2012

Task: Design and build of 2ML/day RO Milk Concentration & Transfer Station.

Where: Rolleston, NZ.

Value: NZ$12M

Features: Project included all disciplines required, including;

  • Civil and building works
  • Milk Receiving
  • RO Plant to concentrate the whole milk (VCF 2)
  • Milk storage and handling systems
  • Rail head load out system
  • Services (steam boilers, refrigeration, comp’ air, CIP)
Projects Ppl 41
Projects Ppl 42

Blenheim Rd Retentate

Year: 2014

Task: 1 storage tank and UF upgrade

Capacity: 2ML/day

Features:

  • Product transfer facility to allow permeate production and handling of surplus milk protein concentrate (out-loaded)
  • Permeate is retained for local milk production
  • UF upgraded to double capacity
Untitled 1

Premium Ice-Cream Plant & Freezer

Year: 2004-2005

Task: Detailed design and project management

Capacity: Premium and House brand Ice-Cream in 100ml to 5L containers, up to 3000kg/hr

Value: NZ$10M

Features: Complete new Ice-Cream Processing Plant, building, 28degC Freezer, ingredient stores and associated services including: aging tanks, flavor tanks, powder recombining unit, two low temperature recycle Ice-Cream freezers, two automatic rotary fillers, coding and conveying system, product recovery system, spiral freezer for rapid hardening, semi automatic shrink wrapping, manual palletising and CIP.

    Projects Ppl 89

    Services Plant Projects

    Pacific Process have been engaged by the client to carry out general plant upgrades on an ongoing and routine basis. Pacific Process continue to add value to WMP by having personnel permanently stationed on site.

    Year: 2007 to present

    Task: General plant upgrades in their Hokitika NZ plant (milk treatment, CIP, receiving evaporation, drying and other works).

    Where: Hokitika, NZ

    Value: Assorted NZ$0.5m to NZ$5m

    Features: Projects focussed on utility / services plant with work including;

    • Engineering design and cost estimations
    • Layout drawings and P&ID updates
    • Chilled water plant
    • Boiler
    • Wastewater treatment
    • Civil and building works
    • Electrical / automation & mechanical installation works
    Projects Ppl 114

    Process Engineering

    E8 Evaporator Project

    This new evaporator allowed CDI to maintain constant feed to their two dryers. They previously had just 2 evaporators feeding 2 dryers, so during the daily evaporator CIP, the respective dryer would not be operational, losing significant productivity.

    Year: 2016

    Task: Project management and engineering package to supervise and engineer the new $68M swing evaporator.

    Where: Visalia, CA. USA

    Value: US$68M

    Features: Project included all disciplines required, including:

    • Project management and engineering
    • Civil and building works
    • Electrical / automation & mechanical installation works
    • Process design and installation
    Project 5
    Project 6

    IF Powder Blending & Packing Facility

    50 cans per minute nominal capacity canning running 900 gm cans line with capacity 2,700 kg / hr. This can line will be fed 24 hours per day without stoppage from the powder handling and blending system. A future can line, nominal 400gm can size, estimated capacity 60 cans per minute, equating 1,500 kg per hour is proposed.

    Year: 2018

    Task: Design and supply of infant powder handling, blending, 3MT/hr packing and storage equipment for product export.

    Where: Shepparton, VIC. Australia.

    Value: AU$2.5M

    Features: Project included all disciplines required, including;

    • Powder transport systems
    • Powder packing plant
    • Powder handling systems
    Projects Ppl 37
    Projects Ppl 38

    General Process Plant Upgrades

    These general upgrades allowed the client to increase their beverage retort capacity, improve their powder packing capability, increased the production rate and ability to manufacture high heat treated powders through the evaporation process.

    Year: 2017

    Task: General plant upgrades in their beverage plant, milk treatment, evaporation and drying milk facility.

    Where: Batavia, NY. USA.

    Value: US$7.5M

    Features: Project included all disciplines required, including;

    • Civil and building works
    • Beverage line retorts
    • Powder packing plant upgrade
    • Evaporator heat treatment systems
    • Dryer pre-heating
    • Skim milk and cream handling upgrades
    Projects Ppl 51
    Projects Ppl 52
    Projects Ppl 50

    Blending Upgrade

    Year: 2019

    Task: To increase blending capacity and decrease blending times through expansion allowing multiple concurrent blending of different recipes

    Where: Auckland, NZ

    Value: NZ$3M

    Features: Pacific Process is responsible for all disciplines required including:

    • Front-end engineering design
    • Procurement, installation and commissioning
    • Subcontractor and project
    • Develop a hybrid automatic and manual factory operation with provision for future expansion
    • Quality assurance in reporting and trending of production
      through operation via SCADA system.
    Projects Ppl 83
    Projects Ppl 82 1
    Projects Ppl 81 1

    KHS CIP upgrade

    Year: 2015

    Task: Install new caustic tank, modify existing caustic tank to handle re-use water

    Capacity: Increase caustic tank from 1,000 L to 3,000 L

    Features:

    • Implemented to existing KHS software system

    • Measured medium volumes to lines (metered)

    • Message hints for step requirements

    Projects Ppl 108

    Water

    Water Treatment Plant

    Year: 2022

    Task: Design, engineering and project management of a new water treatment plant.

    Where: Huntingwood, Australia

    Value: AU$7M

    Features: A complete water treatment plant taking towns water at 150m3/hr through a range of treatment steps. The project included:

    • Ultrafiltration
    • Activated carbon filtration
    • A series of storage tanks (100-150m3)
    • Design of three ring mains delivering water to a range of fillers andher end users around the production plant
    • All automation and control systems
    • All installation works and overall project management
      Projects Ppl 33
      Projects Ppl 34

      Spring Water Processing Plant

      This new facility allowed the client to produce 50m3 / hr of beverage quality drinking water. The water was bottled using Krones proprietary filling equipment

      Year: 2017

      Task: Full turnkey spring water processing
      plant turnkey design and build.

      Where: Sydney, NSW, Australia.

      Value: AU$6M

      Features: Projects generally included all disciplines required, including;

      • Project management and engineering
      • Site installation works
      • Micro filtration and carbon filtration systems
      • Ozone treatment
      • Process design and installation
      Projects Ppl 60
      Projects Ppl 61

      Hot Water Supply Upgrade

      Year: 2023

      Task: To drop hot water loop temperature from 95° to 85°

      Where: Palmerston North, NZ

      Value: US$2.5M

      Features: Project included all disciplines required, including;

      • Subcontract tendering and delivery of the
        complete project

      • The MCC upgrades and required tie-ins were installed over a carefully managed 8 hour shut-down window

      • As a liquid milk plant, the FBNZ plant generally
        never shuts

      Projects Ppl 101 1
      Projects Ppl 102

      Beverage / Alcohol

      Beverage Plant Upgrade

      Plant allows Manitoba dairy farmers the ability to supply all of their milk to the plant. It will produce cream for the Manitoba market, butter for the Canadian market and dry dairy ingredients (milk protein concentrate etc.) for the domestic and international markets.

      Year: 2012

      Task: New beverage manufacturing facility for manufacturing milk protein fortified beverages.

      Where: Batavia, NY. USA.

      Value: US$8.5M

      Features: Project included all disciplines required, including;

      • Civil and building works
      • Powder handling and dumping
      • Powder blending
      • Beverage storage & distribution to 3 x filling lines
      • CIP systems
      • RO Beverage water system with UV sterilization
      Projects Ppl 45
      Projects Ppl 46
      Projects Ppl 47

      Fermenter Tank Upgrade

      Year: 2020

      Task: Design, supply, installation, testing and commissioning of replacement fermenter tanks and clean-in-place systems (CIP)

      Where: Auckland, NZ

      Value: NZ$5M

      Features: Pacific Process is responsible for all disciplines required including:

      • Project Management and Strategic Business Development
      • Project and Contract administration
      • Financial Management and Control
      • Process Engineering, Project Engineering
      • Electrical and Control Engineering, Civil and Structural Engineering and Waste Water Engineering
      • Construction Management
      • Commissioning and Training
      Projects Ppl 77
      Projects Ppl 78

      Gin Distillery

      This new facility allowed the client to produce 50m3 / hr of beverage quality drinking water. The water was bottled using Krones proprietary filling equipment

      Year: 2022 – 2024

      Task: Process design and integration

      Where: Wanaka, NZ

      Value: NZ$6.5M

      Features: Project included all disciplines required, including;

      • Building construction and design co-ordination with the plant and process design
      • Selection and specification of utilities and other services
      • Distillery installation and co-ordination of sub-contractors
        Projects Ppl 72
        Projects Ppl 73
        Projects Ppl 74
        Projects Ppl 70
        Projects Ppl 69
        Projects Ppl 71

        Brewery Upgrades

        Year: 2019

        Task: An upgrade to the existing facility allowing design and/or installation of a range of improvements to throughput and efficiency.

        Where: Auckland, NZ

        Features: 

        • Develop PIDs, piping Isometrics, and layouts for the integration of these new works.
        • Sugar Storage and transfer to batch tanks. Upgrades to the dissolved oxygen water plant (DAW) and increasing storage capacity to 50m3.
        • Installation of a centrifuge for the clarification of fermented beverages, plus a liquid blender for combining raw beverage flows post filtration.
        • Syrup room Safety/ Quality and compliance upgrades, including a HSNO compliance report.
        Projects Ppl 89

        Beverage Plant Upgrade

        Year: 2018

        Task: New beverage manufacturing facility for manufacturing milk protein fortified beverages.

        Where: Batavia, NY. USA.

        Value: US$8.5M

        Features: Project included all disciplines required, including;

        • Civil and building works
        • Automation for the complete installed plant
        • Chilled water plant and reticulation
        • Compressed air
        • Hot water system
        • Beverage storage & distribution to 3 x filling lines
        • CIP systems
        • RO Beverage water system with UV sterilization
        Projects Ppl 96
        Projects Ppl 98
        Projects Ppl 97

        Syrup pasteuriser

        Year: 2015

        Task: Turnkey pasteuriser with additional holding tank

        Capacity: 5,000 L/hour

        Features:

        • Pasteurisation of syrups to buffer tank prior to pre-mixer supply
        • Buffer tank dual purpose as holding tank for non-pasteurised products
        • Modifications to allow mineral water supply to pre-mixer
        • Glucose and dextrose handling systems
        Projects Ppl 101 1
        Projects Ppl 102

        211 Can Line

        Year: 2010

        Task: Turnkey syrup and DI water handling to service Krones pre-mixer and filler Inclusive of additional CIP supply from existing kitchen

        Capacity: 20,000 cans/hour

        Features:

        • Upgrade of batching plant with additional 30kl batching tank and a new sugar tank

        • Syrup transfer line to 2 x 30kl holding tanks

        • Syrup transfer to Krones pre-mixer/filler

        • Installation of ion exchange plant for DI water

        • DI water storage and transfer to pre-mixer

        • Services installation to plant and Krones equipment

        Projects Ppl 111

        PET CSD Line

        Year: 2012

        Task: Water handling to service Krones blow moulder, pre-mixer and filler. Inclusive of an additional CIP supply from the existing kitchen

        Capacity: 28,000 bottles/hour

        Features:

        • Upgrade of batching plant with 3 replacement batching tanks and a 60T sugar tank

        • Syrup transfer line to 2 x 35kl holding tanks

        • Syrup transfer to Krones pre-mixer/filler

        • Installation of ion exchange plant for DI water

        • DI water storage and transfer to pre-mixer

        • Services installation to plant and Krones equipment

        • Installation of additional CIP supply system

        Projects Ppl 114

        General Process Plant Upgrades

        These general upgrades allowed the client to increase their beverage retort capacity, improve their powder packing capability, increased the production rate and ability to manufacture high heat treated powders through the evaporation process.

        Year: 2017

        Task: General plant upgrades in their beverage plant, milk treatment, evaporation and drying milk facility.

        Where: Batavia, NY. USA.

        Features: Project included all disciplines required, including;

        • Civil and building works
        • Beverage line retorts
        • Powder packing plant upgrade
        • Evaporator heat treatment systems
        • Dryer pre-heating
        • Skim milk and cream handling upgrades
        Projects Ppl 114

        Waste

        Waste Treatment Facility

        This plant was built to support the WMP spray drying facility described in the previous slide.

        Year: 2012 – 2014

        Task: Design and supply of Project Management and Engineering for a 6MT/hr WMP Spray Drying Plant Waste Water Treatment Plant.

        Where: Fallon, NV. USA.

        Value: US$7.5M

        Features: Project included all disciplines required, including;

        • Civil and building works
        • WWTP lift station, EQ & Calamity Tanks
        • Primary and secondary DAF
        • MBBR systems with aeration
        • Sludge storage, de-watering (screen) & load out
        • WWTP chemical systems
        Projects Ppl 57
        Projects Ppl 56
        Projects Ppl 55

        Wastewater Treatment

        Year: 2016

        Task: Coordination of the design, equipment supply, installation management and plant commissioning for a wastewater treatment facility.

        Where: Rolleston, NZ

        Value: US$7.5M

        Features: The project scope included;

        • Trade waste balance tanks.
        • Tank instrumentation and agitators.
        • Automation and controls around wastewater discharge
        • pH and temperature control
        • Flow control
        • Caustic and sulphuric acid storage and dosing
        • Wastewater sump and sump pump